Tri-CitiesThursday, November 5
West Richland approves interim data center rules but rejects a moratorium
The Good Day Pasco team
West Richland's City Council approved interim data center rules Tuesday night, with all six members voting yes. TriYakNews.com reports the rules limit data centers to Mixed-Use Light Industrial land. Nonstop Local News says they also ban cryptocurrency mining in all zones and remove a noise exemption.
- Moratorium motion: failed 3-3; it needed five votes
- Interim rules: passed 6-0
- Developer working with Amazon must reimburse the city's review costs
- No data center construction has been approved
Amazon has confirmed it bought 1,000 acres in West Richland. It says the project may have as many as 21 buildings and more than 1,000 jobs, though it hasn't submitted development applications.
Amazon says its West Richland land could hold up to 21 buildings
- 1,000
- acres Amazon says it bought in West Richland
- 21
- buildings at most, Amazon says
- 1,000+
- jobs the project may provide, Amazon says
Source: KONA
If you want to weigh in on the interim rules, the city scheduled a public hearing. It's working toward permanent rules.
West Richland's interim data center rules head to a Dec. 15 hearing
- Nov. 3Council approved interim data center rules and rejected a moratorium motion.
- Dec. 15Public hearing on the interim regulations is scheduled.
- FebruaryPlanning Commission meetings are planned into the month.
- MarchFirst reading of the final ordinance is planned.
Sources: TriYakNews.com, Nonstop Local News
Sources: TriYakNews.com, Nonstop Local News, KONA